PROJECT
Project Name   Ashuganj-Bakharabath Project.
Project Type   Completed
Objective   To Evacuate gas and condensate from Bakharabath gas field to national grid.
Salient Feature   Length 58.50 km, dia 30 inch. Linepipe specification API 5L 60X LSAW. Thickness ----, Coating Hot applied Coal Tar Enamel and CC. Valve station 2



Others   Starting date April 1994, completion date December 1997. Approved Total cost Tk 279.16 crore,(foreign:183.91 Local, 95.25). Actual cost Tk 249.42 crore(foreign:149.00, Local: 100.42)
Contact Information  GM Planning
Download File