PROJECT
Project Name   Dhaka Clean Fuel (Part-GTCL)
Project Type   Completed
Objective   The main objective of the project is to construct ( 20”dia) 60 km High Pressure Gas Transmission Pipeline from Dhanua to Savar.
Salient Feature  



Others   Starting date July 2002, completion date June 2008. Approved Total cost Tk 123.51 crore(foreign:79.24, Local:44.26). Actual cost Tk -- crore(foreign:--, Local: --)
Contact Information  (Engr. Md. Sanowar Hossain Chowdhury) Project Manager (General Manager) Daka Clean Fuel Project (GTCL Part) Tel- 880-2-9356037
Download File  DOWNLOAD